Topsoil Stripping
Often, at the beginning of an earthworks project, the first operation will be to strip the site of topsoil. Topsoil will typically contain a far higher level of organic material, usually including a sod/turf layer; in an industrial context, it will contain a higher level of contamination (nails, glass, oil etc.). It is removed separately for reasons of material reuse and soil stability.
A topsoil strip entails excavating an area by a set depth. For instance, you may strip the entire site by 20cm. This is fairly easy to complete in Kubla Cubed with the ‘Reduce Element’.
-
Stripping calculation completed in its own distinct phase.
-
Earthwork operations that are to be completed after the strip, defined in subsequent phases.